The Macedon BESS project will be charged and discharged at the medium voltage of 66 kV at Gisborne Zone Substation. When there is excess generation in the grid, the BESS will act as load and charge the cells. As generation reduced or demand increases, the BESS will discharge the stored energy to serve the demand.